Several road construction projects are set to begin in Saint John on Tuesday.
Ellerdale Street will be closed between Valley and Margaret streets so crews can install a new water main.
The project is expected to last about 13 weeks.
King Square South will be reduced to one lane from Charlotte Street to Civic #12 until around May 17 to upgrade the existing watermain and install a new storm sewer.
Wentworth Street will be closed from Union Street to Elliot Row until around June 28 as crews install new water and sewer lines and reconstruct the street.